Govt plans to invite bids for Cheyuur project by Jul


The government plans to invite bids for a 4,000MW coal-based power project at Cheyuur in Tamil Nadu by July in the hope of restarting its so-called ultra mega power project (UMPP) scheme, which has been weighed down by ecological concerns and local resistance.

Power secretary P. Umashankar said environmental studies for the Cheyuur project are expected to be completed by April. “We expect to start the award process by June-July,” he said.

The project will rely on imported coal, whose price, including freight charges, are prone to fluctuations. It will thus be crucial for companies to secure coal supplies to bid for the project, as movement in international coal prices would impact input cost.

The Congress-led United Progressive Alliance government wants to set up 16 UMPPs, or power projects that produce at least 4,000MW each, to meet the needs of the world’s second fastest growing major economy after China. India has a power generation capacity of 169,000MW and expects to add 62,374MW by 2012.

Nine UMPPs were originally planned, but only four have been awarded—at Mundra in Gujarat, Sasan in Madhya Pradesh, Krishnapatnam in Andhra Pradesh and Tilaiya in Jharkhand. Two projects, at Girye in Maharashtra and Tadri in Karnataka, had to be abandoned due to local resistance. The bidding process of two others, located near coal mines at Bedabahal in Orissa and Surguja in Chhattisgarh, has been delayed.

Power Finance Corp. Ltd, the nodal agency for awarding UMPPs, extended the deadline for companies to respond to the request for qualification (RFQ) for the Orissa project for a fifth time on 31 January. The new deadline for submission of RFQ applications for the Orissa project is 31 March, and 8 March for the Chhattisgarh project.

“The RFQ deadline for the Orissa project has already been extended till 31 March. We are working with the MoEF (ministry of environment and forests) to find a solution,” said Umashankar.

The power ministry is working with MoEF on a compromise that would allow coal mining to fuel the Orissa project—in an exception to the government’s so-called “no go” policy for coal miners.

In June 2009, MoEF and coal ministry announced “go” and “no-go” areas for coal miners to protect best quality forests.

Mint reported on 26 November that MoEF is ready for a compromise to allow coal mining to fuel the Orissa UMPP.


UMPPs follow a competitive tariff-based bidding in which a special purpose vehicle (SPV) is set up to reduce risk perception and increase investor confidence. This SPV takes care of regulatory requirements such as land acquisition and environmental clearances and transfers these to the winning bidder. Each project requires an investment of around R
s.
20,000 crore.


“After the award of the first three projects, the whole process has taken enormously long,” said Anish De, chief executive at Mercados EMI Asia, an energy consulting firm. “The drive which was there for the earlier UMPP award process needs to be brought back.”

Source: Govt plans to invite bids for Cheyuur project by Jul - Home - livemint.com

Tuesday, February 8, 2011

Power plants insulated from protests

KORBA (CHHATTISGARH): An immense expanse of fine grey fly-ash stretches out to meet the distant horizon, its flat surface rippled by slow-spinning whirlwinds. Seen from the road, the National Thermal Power Corporation's (NTPC) ash pond rises up like an enormous ziggurat of expired embers, with a base nearly 1,120 acres wide and a summit rising 40 feet above Dhanras village near the coal town of Korba in Chhattisgarh.

The self-described “power hub of Chhattisgarh,” Korba district accounts for 11 per cent of the coal produced in India, and 10 per cent of NTPC's national production. Yet the district's emphasis on coal-based power plants has come at a price. A 2009 Central Pollution Control Board study described Korba as “critically polluted” and ranked it the fifth most polluted industrial cluster in the country.

An ash pond is a large patch bounded by raised embankments and used to store the powdery fly-ash produced when coal is burnt in thermal power plants.

“We can't even think of coming here once the summer winds start, the dust is everywhere,” says Jagdish Prasad Devangan, a member of the panchayat of Chhurikala, a village adjoining NTPC's ash pond. It has been 10 years since NTPC's 2,600 MW plant began storing its fly-ash near the village, and now the residents of Chhurikala seem to have had enough.

A High Court petition filed by Chhurikala resident Vinod Pandey accuses the district administration of colluding with private power companies to acquire village land in violation of established norms. The case contrasts two landmark legislations that have shaped the course of industrialisation in India — the Land Acquisition Act of 1894 and the Panchayat (Extension to Scheduled Areas) Act of 1996 (PESA).

Like many parts of Chhattisgarh, Chhurikala's lands are “scheduled” lands, demarcated as “tribal lands” by Schedule V of the Constitution and empowered by PESA, an Act that mandates that village-level gram sabhas be consulted before village land is acquired.

In June 2007, Vandana Vidhyut Limited signed a Memorandum of Understanding (MoU) with the Chhattisgarh government to set up a 540 MW plant in Chhurikala. A public hearing was conducted on December 31 that year. In his report, the sub-divisional officer wrote (in Hindi): “The villagers were informed about the acquisition of private land for industrial needs…the villagers present were not in agreement with giving their lands.”

In May 2008, the sub-divisional officer wrote out another order-sheet that downplayed the significance of the December meeting.

“On 31.12.2007, a Special Gram Sabha was organised in Chhurikala…owing to a lesser number of villagers being present, the proceedings were adjourned…after half an hour, the Special Gram Sabha was recommenced. In which agreement could not be reached in the Gram Sabha,” the order read.

‘Case of urgency'

Soon after, Korba's District Collector Ashok Kumar Agrawal invoked special powers of urgency under Section 17(1) of the Land Acquisition Act 1894 to acquire the land. Section 17 (1) allows a district collector to override all objections and acquire private land “in cases of urgency” within a period of 15 days.

Mr. Agrawal justified his decision on the grounds that “in view of electricity generation and employment in the State, it is very necessary to acquire this land…[the acquisition] is necessary in public interest, as in the absence of the land it would be impossible to build the power plant.”

In the same order, Mr. Agrawal wrote that the acquisition process was exempt from Section 5(a) of the Land Acquisition Act, a section that allows those affected by land acquisition 30 days to register their objections.

Section 4(2) of the Land Acquisition Act authorises a government officer to enter private land and “to ascertain whether the land is adapted for such purpose…to set out the boundaries of the land proposed to be taken.” In this instance, the administration nominated “Vandana Vidhyut Limited” as the survey officer, thereby authorising a private company to act on behalf of the government and evaluate if the land was fit for acquisition by the same company.

Since then, Mr. Agrawal has been transferred as the Collector of Raigarh, another district with large reserves of coal and numerous proposed power plants, and says he is unaware of the Chhurikala petition.

“If Section 17 was used, it must have been done with the permission of the State government,” Mr. Agrawal said in a phone conversation. When asked if he recollected why emergency provisions were invoked this case, he replied in the negative.

Chhattisgarh is a power surplus State, exporting electricity to Delhi, Gujarat and Karnataka. Chief Minister Raman Singh has publicly spoken of using the power sector to generate revenue surpluses which he hopes can be used in development schemes. Yet, the government's push to “urgently” hand over land to private companies has shaken farmers.

Last month, 25 farmers were injured in the Janjgir-Champa district when a protest against a proposed 3,600 MW power plant turned violent. Earlier, 100 farmers in Janjgir were arrested during a protest march when they allegedly attempted to storm the offices of KSK Energy Ventures Limited, the company setting up the plant.

Back in Chhurikala, the existing power plants are looking for more land to store their ever-increasing deposits of fly-ash. “Our ash pond will be full by August this year,” an NTPC official said. “After that we are on the road.”

The official said that NTPC had identified a spot for their next ash pond — Chhurikala.


Source: The Hindu : New Delhi News : Power plants insulated from protests